1. What
are the steps involved in Arc Flash Analysis?
A.
Arc Flash Hazard Analysis or Risk Assessment is a study conducted by trained
safety experts to analyze electric equipment and power systems in order to
predict the amount of incident energy from an arc flash.
According to IEEE std 1584, there are 9 steps involved
in this Arc Flash Analysis, which we are going to discuss here.
Step 1: Collect the system’s installation data:
The largest effort in an arc-flash
hazard study is collecting the data from the site.
Start by reviewing the one-line
diagrams and electric equipment, site, and layout arrangement with people who
are familiar with the site. The diagrams have to be updated to show the current
system configuration and orientation before the arc-flash study starts. The
one-line diagrams must have all alternate feeds. If SLDs are not ready, prepare
them.
Once the diagrams are completed in the basic electric system scheme, enter the data needed for the short circuit analysis. The study must take into account all the sources, along with utilities, and power generators, and for motors of 37 kW and larger than that contribute energy to short circuits. The SLDs should represent all the transformers, transmission lines, distribution networks, system grounding, current limiting reactors and other current-limiting devices, voltage correction capacitors, disconnectors, switchgear, motor control centers (MCCs), panel boards/switchboards including protective coordinating devices, fused load interrupter switches including fuse varieties and sizes, feeders and branch networks, also the motors down to the 600 V or 400 V range, and transformers supplying instrument power. No need to consider the equipment range below 240V unless and until it involves at least one 120 kVA or larger low impedance transformer in its immediate power supply.
From the utility collect the values
of power angle or X/R ratio and the fault current MVA. Most of the utilities
readily supply the data on the existed fault level and power angle values at the point of service. When the data is not
given, Public Utility Commission can be requested the respective utilities to
furnish this information as much as realistic.
Note down the name late details of
all the equipment. Typically this would include voltage/voltage ranges or tap
settings, ampacity, kilowatt or kilovolt amperes, momentary or interrupting
current rating, impedance or transient/ sub transient reactance data, etc. Next
note conductor and cable data along with its installation for all electrical circuits
between the utility and the distribution and control equipment.
Finally, the data from the
protective devices and the transformers i.e., current transformer, voltage
transformer, or control power transformer must be collected. All this data
should present on nameplate details or available at time-current curves.
Otherwise, it should be mentioned in recent maintenance test reports or in
specifications. In any case, the user should verify old data is still up-to-date
by checking with the owner’s representative and, if necessary, by checking in
the field. In some cases the ratings of fuses installed and protective
device coordination settings can be determined by Field Inspection Method.
Step
2: Determining modes of operation of the system:
For a
simple radial distribution system there is only a normal mode of operation,
whereas in a complex system there may be different modes of operations that exist,
which are as follows.
— May be
more number of utility feeders are in working state.
— Tie
breaker in the secondary side bus of the Utility interface substation may be in the open or closed state.
— One or
more primary feeders may exist in a Unit substation.
— Unit
substation having two transformers whose secondary tie is in open or closed
condition.
— MCC
(Motor Control Center) are with one or two feeders, in which one or both feeders
may be energized.
— Connected
generators may run in parallel along with the utility supply or in standby
condition.
Here, It
is very important to obtain the existed short-circuit current for all the modes
of operation that provides both the maximum and the minimum available
short-circuit currents.
Step 3: Determining bolted
fault currents
Input all the
data from the one-line diagrams and the data collection effort results in a
short-circuit analysis. Commercially available software can run thousands of
buses at a time and allow easy switching between different modes of operation.
The simple calculator included in this IEEE 1584 standard can calculate bolted
fault currents of the radial systems up to 600 V. Find the symmetrical RMS value
of the bolted fault current and X/R ratio at each and every point, for all the locations where people
work by taking each of these points as a bus. For all the modes no need to run
all the buses because bolted fault currents of some buses will not be affected
by all the modes. Consider an example, if we connect secondaries of transformers
together, then primary side fault energy may not increase.
It is necessary to include all the
cables because the error on the high side may not increase safety always, it may
decrease it. Reduced fault currents may exist longer time than currents of
higher magnitudes as mentioned in protective-device coordination (TCC) curves.
The arc
fault current at the required point and the magnitude of that fault current passing
from the first upstream protective device to downstream must be selected.
This
arc fault current magnitude mainly depends upon the bolted fault current. The magnitude of this bolted fault current in the protective device can be obtained
from the short-circuit analysis by looking at a one-bus-away run. This will
separate faults that occur in a normal feeder, alternate feeder, and downstream
motors.
Then the arc fault currents can be calculated. The obtained arc fault current magnitude will be lower than that of the bolted fault current magnitude due to arc impedance, mainly for applications < 1 KV. For medium-voltage levels, the bolted fault current is still greater than the arc current, and it should be calculated.
Step 5: Finding the coordinating device characteristics and the duration of the arc existence
Updated
system TCC curves can be obtained from the field survey. If not found, it is
better to create them with the help of commercially available software easily.
Otherwise, for a simple study, we can use protective device characteristics,
which were present in data from the manufacturer.
TCC curves of fuses obtained from the manual may contain both clearing time and melting times. If so, use the clearing time. If they provide only the average melting time, add 15% of that, i.e., up to 0.03 seconds, and 10%. The manufacturer’s TCC curves include both tripping time and clearing time in case of circuit breakers having integral trip units.
For circuit breakers operating with relays, the curves show only the relay operating time in the time-delay region. The recommended circuit breaker operating times were shown in the following table. Opening times for the mentioned circuit breakers can be verified by the manufacturer’s data.
Type and Rating of the Circuit Breaker |
Opening time at 60 Hz (cycles) |
Opening time (seconds) |
Low voltage (molded case) (< 1000 V) (integral trip) |
1.5 |
0.025 |
Low voltage (insulated case) (< 1000 V) power
circuit breaker (integral trip or relay operated) |
3.0 |
0.050 |
Medium voltage (1–35 kV) |
5.0 |
0.080 |
Some high voltage(> 35 kV) |
8.0 |
0.130 |
As shown in the
following table-2, document the system voltage and the class of equipment for
each and every bus. This will allow the application of equations based on standard
classes of equipment and bus-to-bus gaps as shown in the following table.
Classes of equipment |
Typical bus gaps (mm) |
15 kV switchgear |
150-152 |
5 kV switchgear |
102-104 |
Low-voltage switchgear |
30-32 |
Low-voltage MCCs and panel boards |
24-25 |
Cable |
12-13 |
Other |
Not Required |
Arc-flash
protection always depends only on the incident energy on the person’s face
and body at the working distance, but not on the incident energy on the
person’s hands or arms. Based on the percentage of the person’s skin which is
burned the degree of injury classified. As the head and body forms a large
percentage of total skin and injury to these areas becomes much more life
threatening than the burns on the extremities. The typical working distances were
mentioned in the following table. (Table-3)
Table 3—Classes of equipment and typical working distances
Classes of equipment |
Typical working distance (mm) |
15 kV switchgear |
910 |
5 kV switchgear |
910 |
Low-voltage switchgear |
610 |
Low-voltage MCCs and panel boards |
455 |
Cable |
455 |
Other |
To be determined in field |
Typical working distance is defined as “ the sum of the distance between the worker standing in front of the equipment, and
from the front of the equipment to the potential arc source inside the equipment”.
Any good
software for calculating incident energy must be selected. In some cases, the
equations in the models, are embedded in the software program or worksheet. In
some programs, the problem is solved only at one bus at a time; whereas some
programs offer the facility that, hundreds or thousands of buses can be solved
simultaneously. After getting incident energy, generate Arc Flash Labels.
To find the Arc flash-protection boundary, the equations for finding incident energy can be solved for the distance from the arc source at which a second-degree burn could occur.
The incident energy must be set at the minimum value beyond which a second-degree burn could occur. The programs include the flash-protection boundary based on incident energy of 5.0 J/cm2
2. What are the standards we follow in Arc Flash Risk Assessment?
A. No individual code or standard defines all
the requirements for arc-flash safety. Arc flash safety is based on the
cumulative requirements found in several codes and standards, which include
OSHA, NFPA70E, IEEE1584, NFPA70, NESC, which will be discussed as follows.
1. OSHA: Occupational Safety and Health Administration
Federal laws and regulations address a variety of safety issues, which include electrical safety requirements which are necessary to safeguard the employees in the workplace. This OSHA addresses electrical safety requirements for all employee workplaces, along with commercial office and industrial environments. The points we should notice include:
2. NFPA 70E: Electrical Standard for safety in the Workplace
NFPA 70E
gives specific requirements for selecting Personal Protective Equipment (PPE)
and warning the workers regarding equipment’s potential electrical hazards.
Employers are advised to adopt and follow NFPA 70E standard and to comply with
OSHA’s general duty clause. Refer the Article 90 of NFPA 70E for a clear
description of what the standard does and does not cover.
This
Arc Flash PPE categories method is to determine the equipment’s Arc Flash PPE
Category, which is previously known as the Hazard/ Risk Category (HRC), this
will tell you the PPE required for the task. As described in the tables, if a
task is not listed, or the exact conditions are not met, this method is useless,
and an incident energy analysis will be required. For this reason, it is better
to follow the Incident Energy Analysis method instead of Arc Flash PPE method
to generate arc flash labels for all equipment.
In
NFPA 70E 2015 edition, unlike previous editions of NFPE, here employers are not
permitted to list out a PPE Category on an arc flash label if the label is
provided with the available incident energy.
This
NFPA 70E is a standard adopted only by employers not by all local
jurisdictions. Though NFPA 70E is not officially followed by OSHA, employers
may utilize NFPA 70E in compliance with OSHA.
It is a standard which is having methods and
procedures to calculate the amount of Arc Flash Incident energy to which the
employees may expose. The results of this incident energy calculation are used
to suggest the appropriate PPT according to NFPA 70E. Calculating the existed
incident energy needs the data about short circuit and over current protection
settings because without performing short circuit and protective device
coordination studies, we cannot perform arc flash hazard analysis. The arc
flash hazard analysis needs the field data to cross verify with the facility’s
electrical distribution and overcurrent protective device settings.
NFPA 70 also called National Electric Code (NEC) is a standard deal with safety of persons, property or equipment from electrical installation hazards. In Article 110.16 of NEC, it is stated that electrical equipment that is likely to require interaction while energized shall be field-marked to warn workers of potential electric arc-flash hazards. NEC-2017 version extended the article 110.16 requiring more stringent arc-flash labeling requirements for service equipment of rating 1,200 amps or more, essentially requiring the equipment to be assessed for arc-flash risk. According to NFPA 70E OR IEEE1584, if an arc flash label is provided, then no need for this NEC labeling. This NEC is regionally adopted and enforced by states and local municipalities; whereas a new arc-flash labeling system will be enforced by local jurisdictions that have adopted NEC 2017.
0 Comments